- Execute RCC and allied civil works for the assigned tower as per Good-for-Construction (GFC) drawings and approved methodology.
- Plan and supervise the daily Mivan formwork cycle – de-shuttering, shifting, alignment, shuttering, reinforcement checking and concreting – to achieve the targeted slab cycle.
- Coordinate line, level and layout marking with the survey team; verify shuttering alignment, plumb and dimensions before every pour.
- Raise pour cards / checklists and obtain QA/QC and consultant clearances before concreting; supervise concreting including cube sampling and workability checks.
- Monitor and record daily labour deployment, contractor workmen output and material consumption; report daily progress (DPR) to the Sr. Project Engineer.
- Coordinate with MEP teams for sleeves, conduits, inserts and openings before concreting to avoid rework and chipping.
- Ensure curing, de-shuttering as per stripping-time norms, and rectification of honeycombing / surface defects per approved procedures.
- Certify contractor measurements at site jointly with the billing team; maintain site records, registers and as-built markups.
- Enforce EHS requirements at the workfront – safe working platforms, edge protection, housekeeping and toolbox talks with the safety team.